Projects
Chasetown Specialist Sports College was originally built in 1970 as a temporary structure, the College has worked hard over the years ensuring that the building is maintained for the students and staff using it. Over the past 12 months more work has been carried out to benefit all who use Chasetown.
Completed Projects
Project Title |
Timescale |
Cost |
|---|---|---|
New furniture for the science rooms and new blinds |
December 2007 |
£3,000 |
New furniture for the Library - reception desk, tables and chairs, 8 desk computer pod and chairs |
January 2008 |
£8,500 |
Refurbishment of Room 13 - Painted, new desks, chairs computer stools and carpets |
October Half Term 2007 |
£3,000 |
Refurbishment of the Theatre - new flooring and seating |
Christmas Holiday 2007 |
£21,000 |
Refurbishment of the canteen - painted, new signs |
Easter Holidays 2008 |
£2,000 |
Windows - New windows at the back of the school (Science Department and side of the school by English and Maths rooms) |
Completed in two phases October and February Half-Term |
£82,000 plus additional funding from the local authority |
CCTV - new CCTV for college site |
February Half Term 2008 |
£17,000 |
Refurbishment of External Doors |
February 2008 |
£6,000 |
Moving of Mentor Room and Refurbishment of the Zone |
Easter Holidays 2008 |
£1,500 |
New Year 8 and 9 Toilets and Disabled Toilet |
Summer Holidays 2008 |
£60,000 |
New CC3 Curriculum Network |
April 2008 ongoing |
£98,000 |
New Conference Room for use by students and staff |
Summer 2008 |
£97,000 |
Refurbishment of Science Room using LA funding |
February 2009 |
£40,000 |
Refurbishment of Sixth Form Area |
Summer 2009 |
£65,000 |
New Art Block Roof |
October 2007 |
£30,000 |